Street Maintenance 2024
Project ID:
4014
Project Type:
Capital Project
Project Status:
Under Construction
Property Owners:
City of Wilsonville
Contractor:
Knife River
Funding Source:
Road Maintenance Fees
Location:
See maps
See map: Google Maps
This project aims to:
- Rehabilitate the pavement on Boberg Road, Boones Ferry Road (between Wilsonville Road and Bailey Street) and Bailey Street (east of Boones Ferry)
- Bring pedestrian crossings along Boones Ferry Road between Wilsonville Road and Bailey Street to ADA Standards
If you have questions about this project that the website doesn’t address, contact:
Jason Rice at 503-387-7300
Status Updates
Project schedule/milestones are shown below.
- June 24, 2024 - Begin Construction
- August 31, 2024 - Complete Construction
A schedule with great detail will be available mid-June.