Corral Creek and Rivergreen Lift Station Rehabilitation
Project ID:
2105
Project Type:
Capital Project
Project Status:
Built
Design Engineer:
Murraysmith
Contractor:
TBD
Funding Source:
Wastewater rates
Location:
Corral Creek & Rivergreen LS Rehab
Wilsonville,
OR
97070
See map: Google Maps
PROJECT DESCRIPTION
Equipment upgrades to the Corral Creek and Rivergreen wastewater lift stations.
STAFF CONTACTS
Staff can be reached via telephone at 503-682-4960.
Mike Nacrelli, Senior Civil Engineer
Status Updates
- Construction began in February, 2023 with completion anticipated in August, 2023.