Brown Road Improvements
This project was identified in the Transportation system master plan as Urban Upgrade Project UU-03, and approved in the West Side Urban Renewal plan. The project provides urban upgrades to Brown Road to more closely meet current City Standards. The section to be improved is approximately 1,900 feet long and extends from SW Wilsonville Rd to SW Evergreen Dr. Urban upgrades improve connectivity by adding bike lanes, sidewalks, and turn lanes that accommodate access to adjacent neighborhoods.
If you have questions about this project that the website doesn’t address, contact:
Marissa Rauthause at 971-325-4080
Status Updates
Anticipated Project schedule is shown below.
- Predsign: Summer 2024 - Winter 2024
- Design: Spring 2025 - Spring 2026
- Construction: Spring 2026 - Winter 2026
- Completion: End of 2026