Villebois Tonquin Meadows

Tonquin Meadows 0716
The planned three (3) phases of Tonquin Meadows covers Preliminary Development Plan (PDP) 3 and 4 of Villebois SAP East, and includes a total of 298 homes, the majority of which will be single-family, detached homes.  

The development encompasses an area north and west of Lowrie Primary School, east of the former SW 110th Avenue, south of SW Boeckman Road, and west of the Coffee Creek wetlands.

Tonquin Meadows Phase 3 will be 56 lots just west of the Coffee Creek wetlands and north of Lowrie Primary School.  Construction of homes is expected to occur in 2017 and 2018.

Staff Contacts

Staff can be reached by calling 503-682-4960.

Project Information

  • Applicant: Polygon Northwest Company
  • Property Owners:
    • Polygon at Villebois V LLC
    • Polygon at Villebolis III LLC
    • Sparrow Creek LLC
    • City of Wilsonville
    • Metro
  • Design Team: Pacific Community Design, Inc
  • Contractor: Northwest Earthmovers, Inc.
  • Funding Source: Mostly private with some Street SDC's for bike lanes on Villebois Drive, Costa Circle and partial construction of Coffee Lake Drive. Some Water SDC's for oversizing watermain. 100% Street SDC's for construction of Villebois Drive between Boeckman Road and Coffee Lake Drive.

Project Status

  • Construction: Home construction underway. 

Public Works Permit issued.
An amendment approving a SAP/PDP Phasing Amendment was approved by the Planning Director on November 19, 2013.  The phasing of PDP 3 and 4 of SAP East was originally based on different ownership of the properties.  Polygon acquired all of the properties and reworked the phasing without regards to previous ownership:  

 The DRB approved the Staff Report and Conditions of Approval for SAP East, PDP 3 on November 15, 2012:

The DRB approved the Staff Report and Conditions of Approval for SAP East, PDP 4, on November 15, 2012