Bids & Proposals

  
Sign-up for Email Notifications - Receive an email when an update is made to the Bids & Proposals webpage.

  RFP/RFQ/SOQ
 None at this time.
 
  RFP/RFQ/SOQ RESULTS
Water and Sewer Rates and SDCs

  • FCS Group 
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Manufacture and Installation of Vinyl Bus Decals


  • Gillespie Graphics - 297 points
  • Professional Sign & Graphcs - 266 points
  • Turbo Images, Inc. - 255 points
  • Signature Graphics, Inc. - 229 points
  • Visual Marking Systems - 214 points
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Sign Design and Wayfinding Signage Plan 


Thanks to all who submitted a proposal for the Sign Design and Wayfinding Signage Plan Project (CIP#3003). The internal project team met February 1, 2018 to review the proposals and has chosen Alta Planning and Design as best meeting the city’s needs for this project. Please consider this notice as the City’s intent to award the project to Alta Planning and Design.

If you have any questions or need additional information regarding the award of this proposal, please feel free to contact Chris Neamtzu, Planning Director, at 503 570-1574.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Equitable Housing Strategic Plan Consultant


  • POSTPONED UNTIL FURTHER NOTICE
 PROJECTS OUT FOR BID
None at this time.
 BID RESULTS 

Transit Stop Improvements 

  • Brown Contracting, Inc. - $43,858.00 
  • 3 Kings Environmental, Inc. - $65,040.80
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
WWTP Outfall Replacement 



  • Northbank Civil & Marine - $1,123,560 
  • Advanced American Construction - $1,370,000
  • James W Fowler Co. - $1,785,000
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Charbonneau High Priority Utility Repair - Phase III  



Bid Tabulation

  • Braun Construction - $921,783.00
  • Elting Northwest - $1,179,167.00
  • Trench Line Excavation - $1,187,400.00
  • Emery & Sons - $1,234,519.00
  • Moore Excavation - $1,331,437.00
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 

Tooze Road - 110th to Grahams Ferry Road

 


Revised Bid Schedule Results

  • Tapani, Inc. - $4,588,466.25
  • Emery & Sons Construction Group - $4,595,995.00
  • Goodfellow Bros, Inc. - $4.652,798.00
  • Kerr Contractors - $4,666,296.00
  • Elting Northwest, Inc. - $4,811,820.00
  • Nutter Corporation - $4,899,569.22
  • Pacific Excavation, Inc. - $5,994,000.00
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Fred Meyer Exit Modifications 



  • Brown Contracting - $191,649.00 
  • Kerr Contractors - $262,855.00
  • Pacific Excavation - $285,000.00
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

I-5 Exit 283 Southbound Entrance Ramp Modifications 



  • Kerr Contractors - $562,578.00
  • R & R General Contractors, Inc. - $610,000.00
  • Wildish Standard Paving Co. - $653,855.60
  • Benchmark Contracting - $692,458.00
  • James W Fowler Co. - $798,457.00
  • Pacific Excavation - $865,000.00
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Library Improvements 



  • 2KG - $1,054.000.00  
  • First Cascade Corporation - $1,101,614.00
  • Yorke & Curtis - $1,235,046.00
  • Brockamp & Jaeger, Inc. - $1,236,384.00
  • Woodburn Construction Company - $1,269,690.00
  • Cedar Mill Construction Company - $1,294,400.00
  • Ross Builders - $1,348,366.00